I had to pay my DNO for the G99 process - the existing G99 likely would have been sufficient anyway, given that the 7.36kW remained for export limitation. However, it did allow me to ensure that I had approval for up to 11.6 kW of inverter capacity instead of the previous 5kW installation. No issues seen in the 5-6 weeks since completing the install, and I’m up over half a MW on where I’d have been otherwise.